St Francis Cottage Bed and Breakfast Going Up Quickly!
After three and a half years of planning and the roller coaster ride of bureaucracy, a lot has been accomplished since breaking ground in late May of this year. Under the guiding hand of Cole Poorman of
America's Home Place, the foundation, framing, windows (Oswaldo Nunez Framing), are all in place.
Electric wiring and
plumbing are well on the way.
HVAC plans have been established and the work should start next week. Kitchen
cabinets have been measured and will arrive in about 8 weeks. Siding has been delivered and the west wing is covered. Most of the
internet and cable infrastructure has been installed. And the
fire sprinkler system is nearing completion. It's all a bit overwhelming, but we love it!
Our applause and thanks go out to all the hard working crews on each part of this job. The heat and humidity has been pretty brutal, but progress continues amidst Chattanooga's hot, hot summer of 2016.
 |
| Progress as of July 29, 2016. Though not pictured, siding has been delivered on site. |
Read more to see more progress . . .